Place of Origin:
China
Brand Name:
Ruideer
Certification:
CE
Model Number:
336/4412/5518
Furnace Type | Horizontal type(Max Working pressure:58bar/98bar | |||
RDE-3312-N | RDE-4412-N | RDE-5512-N | RDE-5518-N | |
Usable Space (W*H*L) | 300*300*1200mm | 400*400*1200mm | 500*500*1200mm | 500*500*1800mm |
Max.Charge Load | 300kg | 500kg | 1200kg | 1500kg |
Power Rating | 320KVA | 320KVA | 430KVA | 600KVA |
Heating Zone | 2/3 Zones | 3 Zones | 3 Zones | 3 /4 Zones |
Cooling time | ≤5h | ≤6h | ≤7h | ≤8h |
Empty furnace, cooling from sintering temperature 2100℃ to 100℃. (water temperature≤26℃, water pressure 2-3bar, 55bar(95bar)≤Ar pressure≤58bar(98bar). |
||||
Service Life | 20years/6000furnace cycles | |||
Max. Working Temp | 1800℃ | |||
Temperature Measurement | Special design High temperature W-Re5/26 Thermocouple | |||
Max Vacuum Degree | 1Pa (under cold, empty, dry furnace) | |||
Leakage Rate | 3Pa/h (Average value under cold, empty, dry furnace) | |||
Wax Collection | ≥98%(Argon gas negative dewaxing, 3-time average value) | |||
Forming Agent | Paraffin,PEG,Rubber,(C12H22O5)n etc. | |||
Input gas | N2, Ar, H2 | |||
Functions |
Automatic Positive Pressure, Negative Pressure Leak Detection Ar Negative Pressure Dewaxing/H2 Micro Positive Pressure Dewaxing Vacuum Sintering Partial Pressure Sintering (Static, Dynamic) Pressure Sintering Rapid Cooling Fully-automatic control & Safety interlock& Breakpoint continuing heating & Wireless remote control& Self-diagnosis |
How is the Rapid cooling system operating in sintering furnace?
The fast cooling of the pressurized sintering furnace is divided into two stages. The first stage is to cool down naturally under the pressure environment, and the heat preservation door is closed; the second stage is to open the heat preservation door after reaching the set temperature to make the high pressure in the furnace. The argon gas passes through the radiator on the furnace door to quickly take away heat. When the furnace top furnace temperature or the furnace door radiator temperature reaches the upper limit, the heat preservation door is closed again, and the furnace top furnace temperature or the furnace door radiator temperature drops accordingly. When the temperature of the top furnace or the radiator of the furnace door drops, when the temperature is lower, the insulation door is opened again. After several cycles, the temperature of the furnace top or the radiator of the furnace door no longer reaches the upper temperature limit, and the insulation door is always open.
Cycling of inert gas atmosphere through water cooled heat exchanger
The gas is cycled out of the furnace into a heat exchanger and pushed back after cooling down into the furnace chamber.
For this application, the furnace must be equipped with a roots pump to be able to cycle the gas through the heat exchanger. After cooling down the gas the roots pump pushes the cold gas back into the furnace again, directly into the retort with the load. The sample is directly surrounded with the freshly cooled gas.
Cycling the inert gas reduces the gas consumption, which lowers the process costs. Generally, the cool down time of the empty furnace is reduced by a factor of two using this option. The lifetime of the sensitive heating elements and insulation will be reduced using this fast cooling option.
• Design standards
The equipment is designed in accordance with the pressure vessel requirements of the Quality and Technical Supervision Bureau, and is qualified after pressure testing and shipped. The electrical design and construction meet national standards.
• Installation pre-test and pre-acceptance
The equipment is fully assembled in our factory, including all pipelines, vacuum pipelines, process gas pipelines, cooling water pipelines, compressed air pipelines, etc. Pre-testing can be carried out after installation. At the customer site, pipelines other than the equipment are provided by the customer. The installation also includes the connection of all cables. At the customer site, the main cable connecting the power cabinet is provided by the customer. After installation, we conduct vacuum and positive pressure leakage tests on the entire equipment, as well as mechanical and electrical function tests.
• Disassembly and transportation
The equipment will be disassembled in several large parts, packed in a standardized manner, and loaded into the transport vehicle.
• Customer site installation and commissioning
The Redel after-sales engineer will lead the team to complete commissioning, product trial burning and other work within 20 working days. The customer needs to make appropriate preparations and provide the necessary tools, such as hoisting and lifting equipment. And provide installation personnel support (it is recommended to have 1 mechanical personnel and 1 electrical personnel).
• Final acceptance
After installation and commissioning, the equipment can be finally accepted in accordance with the requirements of the technical contract.
• Training
Our after-sales engineers will provide a systematic and complete on-site training, including operation, maintenance, troubleshooting, etc.
• Technical data delivery
To ensure safe operation and equipment maintenance, the following technical data will be provided to customers:
1. Equipment installation layout
2. User manual
3. Spare parts list
4. Electrical drawings
5. Component manual
FAQ
Q: Are you a factory or trading company?
A:We are China leading high-temperature vacuum furnace manufacturer with over 10 years’ experience.
Q: Do you have customization or OEM service??
A:Yes,we have powerful R&D team and high-tech equipment.So we can not only supply the regular model,but also the customizable furnace as the repuirment of our clients.
Q:What's your advantage?
A:
l Quick response to your enquiry
l High quality control
l Stable supply chain
l Timely delivery
l Excellent after-sales service
Send your inquiry directly to us